Subsections
As of 1995, the campus power consumption varied anywhere from 7500 kW on winter holidays to 24000 kW on peak summer days. While this is a significant spread, the campus did not spend more than 500 hours below 10000 kW for the entire year of 1995. Figure 7 shows a plot characterizing the nature of power usage on campus. Note that the campus maintains an hourly usage above 10 MW for over 8000 hours per year. To further characterize campus usage, the load factor for each month was calculated. Figure 8 shows the campus load factors for 1995. The load factor was determined by dividing the actual kWh usage for the campus in a given month by the kWh usage if the campus operated at the month's peak electrical demand for each hour the entire month.
As you can see, the load factors are quite high, with December 1995 turning in the lowest value of 68.4% and August 1995 the highest of 80.4%. Such high load factors mean that the difference between the highest and lowest demand for a given month is quite small. So from season to season consumption may differ, but is generally flat throughout a month.
The demand charge varies depending upon the magnitude of customer demand: the first 2000 kW of demand is charged at one rate, the next 3000 kW is charged at another rate, and finally, all kW above 5000 is charged at a final rate. The rate decreases as the demand increases, and the rate is lower for the off-peak months (October - May) than the on-peak months (June-September). Also, there is a provision which allows for an economy demand charge if the peak demand for a given month occurs in a off-peak time during the day (8:00 AM -12:00 PM).
The energy charge varies depending upon the time of day it is used. The late night and early morning hours are least expensive, while the afternoon and early evening hours are the most expensive. Also, weekend power usage comes at a discount. Like the demand charges, energy charges are lower in the off-peak months, and there is an adjustment to the time of day structure. A copy of the TOU-4 rate is available in the Appendix B. It discusses the variations in time periods as well as the specific charges for each time period for both demand and energy.
To compile each month's bill, both the TOU-4 demand and the energy charges are calculated based upon the 1991 year. The demand charge is calculated by using the highest power reading for a given meter in a given month in 1991. The resulting charges for demand and energy are then added together to form the standard charge, or TOU-4 portion, of the bill.
The RTP portion of the bill, the incremental charge, is calculated by first determining the difference between the power consumption for the current year and the 1991 base year (can be either positive or negative) for each half hour period during the month. The difference is then multiplied by the cost of the RTP power for that half hour, then added (or subtracted) from the running total for the month. At the end of the month, the cumulative total incremental charge is added (or subtracted) from the standard bill to determine the final monthly bill. The cost of RTP power, which changes hourly, is determined by Georgia Power one day ahead and is available for downloading at 4:00 PM of the preceding day.
The only adjustment that is made to the 1991 data which makes up the CBL is to shift the days so that the weekdays for the 1991 year and the current year are aligned. The CBL, once agreed to, is permanent and usually only changed for a permanent removal of equipment, installation of energy efficient equipment, or a demonstrated decrease in total power consumption that causes the new power consumption for the year to fall below that of the CBL. In order to establish a new CBL, the consumer must revert to the old tariff for an entire year. The new year's power data can then be used as the new CBL.
The campus base thermal load is roughly 15,000 pounds per hour, with a peak load of greater than 75,000 pounds per hour. Figure 9 and 10 show how the campus gas requirements vary with temperature.
Both plots use degree days to characterize the daily temperature. Degree days are a measure of how far the average daily temperature deviated form a 65 degree Fahrenheit norm. Therefore, 0 degree days represent a day for which the average daily temperature was 65 degrees, 10 degree days represent a day for which the average daily temperature was 75 degrees, and -10 degree days represent a 55 degree average daily temperature.
It is obvious from Figure 9 that gas usage is high during the cold winter months and decreases steadily to the base load throughout the spring and summer, then begins increasing again as fall progresses. Figure 10 shows a regression plot which directly relates gas usage to degree days. As the degree days decrease (negative degree days), gas usage increases, and as the degree days increase (positive degree days), gas usage decreases, but only to a limiting value. This limit can be attributed to campus hot water needs or other non-space heating loads. The figure shows all gas usage days from the past year, including the curtailment days. However, the curtailment days were not used when calculating the regression plot in Figure 10.
The steam turbine generator also seems to be a poor choice. Steam turbines have the lowest fuel-to-electrical ratio of any of the types of cogeneration systems. In order to produce a sizable amount of electricity with steam turbines, the boilers would have to operate at full load and a great deal of steam would have to be discarded. It would be possible to install small steam turbines intended to directly replace electrical drives, but the number of steam turbines required would require a great deal of maintenance, and the increased cost of installing smaller turbines throughout campus makes steam turbines an economically unattractive option.
The gas turbine naturally lends itself to the campus requirements. The large variety of sizes in the 3 MW to 15 MW range allows for precise sizing of the turbine unit. Since the campus boilers are already fired with natural gas, with No. 2 oil as a backup, the fuels used by the gas turbine are already available. Gas turbine units are compact and can be installed either inside or outside. The high reliability of a gas turbine unit means that it can operate continuously with only a minimum of downtime or unscheduled maintenance. The exhaust from the turbine is rich enough in oxygen to sustain supplementary firing, which allows greater flexibility in meeting the changing campus steam loads. Finally, the low capital cost of a gas turbine generator system makes it an extremely attractive option form an economic point of view.
Once the prime mover has been chosen, a number of strategies were evaluated to determine the best economic return. The economic attractiveness of each strategy is inescapably linked with the utility rate structure under which the location is served. Each strategy can return good economic results if a given rate structure lends itself to the strategy.
The following three strategies were chosen for the study; base loading, peaking, and thermal following. For the base loading strategy, the turbines are operated at full load at all times. As much steam is recovered as is required to meet the campus steam load, with the remainder discarded in a condenser. During times when the steam load exceeds the turbine's ability to generate steam, additional steam is generated in the existing boilers. Obviously the heat recovery for a base loading strategy is higher during the winter when the thermal load is high, and lower in the summer, when the thermal load is low.
The peaking strategy studied requires that a certain minimum electrical price be met before the generator is operated. This minimum price was determined by using an assumed cost of fuel to calculate the cost of generating 1 kWh of electricity using the gas turbines. When the minimum price of electricity being charged to campus by Georgia Power is exceeded, the generator is switched on and operated at maximum load, with enough heat recovery to meet the campus steam load. A more detailed discussion of the economic calculations used in the peaking strategy is carried out in Chapter VII.
Finally, the thermal following strategy varies the gas turbine load
to meet the campus thermal load. During the times when the generator cannot
meet the steam load, the generators operate at full load, with the remainder
of the steam being generated by the existing boilers. All electricity generated
during the thermal following strategy is used within the campus.