

Next: Conclusions and Recommendations
Previous: Campus Analysis
Subsections
RESULTS
Summary of Economic Results
For each operating strategy and generator size, a simple payback was calculated
using the economic data in Chapter VII. The economic
analysis could be carried to as great a degree of detail as desired, but
ultimately, the attractiveness of each operating strategy relative to each
other can easily be shown by using just the simple payback method.
Base Load Operating Strategy
Figure 11 shows the 5 MW generator to be the best choice
for a base load strategy, with a payback of 4.1 years. None of the generators
has a payback greater than 6 years. Each of the four different sizes return
attractive economic results. However, the smaller the system, the higher
the percentage of available heat recovered from the exhaust and therefore
the better total efficiency of the system. Recall that the minimum steam
load for the campus is roughly 15,000 pounds per hour. This would directly
translate to a 2.3 MW generator. In other words, a 2.3 MW generator would
be fully loaded, both electrically and thermally. It is reasonable then
to assume that a 2.3 MW generator would return the best economic results
of any of the systems considered. However, recall from Figure
3 in Chapter 4 that as the size of the turbine generator set decreases,
the equipment cost per kW increases dramatically. Also, the fuel-to-electrical
efficiency of operation suffers. These factors tend to push the optimum
sized turbine generator to a slightly larger size.
Figure 11 - Simple Payback for the Base Loading Operational
Strategy.
The base loading strategy returned the best economic results of the
three operating strategies considered. Because of the nature of the rate
structure that serves the campus, the electrical generating capacity of
the systems considered directly offsets the electricity purchased under
the TOU-4 portion of the structure. This is by far the most expensive electricity
the campus buys, so the economic benefits of eliminating the purchase of
this expensive electricity are considerable. Also, the prime movers under
this operating strategy operate at full load at all times. This maximizes
the efficiency of operation, longevity of machinery, and minimizes the
control and monitoring of the system.
Peaking Operating Strategy
Figure 12 shows the economic results of the peaking
strategy. The larger the turbine generator, the quicker the payback. But
even with the largest turbine, the payback is approximately 28 years. Obviously
this is unacceptable when considering a project on the basis of economics.
The 10 MW unit offsets the largest amount of expensive electricity and
has the best payback of the four turbine sizes studied. The smallest turbine,
the 4000 kW unit, has the highest cost per kW and offsets the lowest amount
of expensive RTP electricity. Therefore the smallest turbine has the worst
payback.
Figure 12 - Simple Payback for the Peaking Operational Strategy.
The peaking strategy returned poor economic results. The major factor
contributing to this is the electrical rate structure. In order to remove
load from the TOU-4 rate structure, the generator must operate continuously.
With the peaking strategy this is not the case. Since no permanent removal
of load from the power company can be guaranteed, no adjustment to the
CBL may be made, and all electricity generated offsets RTP electricity.
While the cost of the electricity that the turbines are offsetting is high
on average (~ $0.469 per kWh), the RTP price is only above the break even
cost for 370 hours during the year. This means that although the savings
are large while the turbine is on, the lack of operating hours requires
many years before the initial capital investment can be recovered. Furthermore,
the highest cost for electricity occurs during the summer months, times
when the thermal load is low, and the amount of recoverable heat is minimal.
Thermal Following Operating Strategy
Figure 13 shows that the thermal following strategy
displays an economic trend exactly opposite of the peaking strategy. The
4 MW turbine has a payback of 6.8 years, which increases to 15.1 years
for the 10 MW turbine. As the prime mover size decreases, the economic
attractiveness increases. This is due to the utilization of the gas turbine.
As the turbine size decreases, the turbine operates at nearer full load
operation for a greater portion of the time, increasing fuel-to-electrical
efficiency. Remember that as the gas turbine size approaches 2.3 MW, the
gas turbines approach a fully loaded operational condition, as in the base
load operational strategy discussed earlier. The 10 MW turbine only operates
at 40% load on average, an extremely low value for a gas turbine. Since
gas turbines do not respond well to changing loads or less than full load
operation, it is undesirable to operate a gas turbine at such low load
factors.
Figure 13 - Simple Payback for the Thermal Following Operational
Strategy.
The thermal following strategy produces some avoided electrical cost
at the TOU-4 rates, but not to the extent that the base loading strategy
does. The thermal following strategy only offsets the amount of TOU-4 electricity
that directly coincides with the minimum campus steam load. As mentioned
earlier, this is approximately 2300 kW. The remaining electricity generated
above the 2300 kW threshold offsets electricity at RTP prices. During the
winter months when the thermal load is high and the gas turbines are more
fully utilized, a larger portion of the electricity generated by the turbine
comes off the less valuable RTP portion of electric service. The summer
months are exactly opposite. The gas turbines are operating at less than
full load and therefore produce less electricity during times when electricity
is most expensive. The seasonal dependence of the campus thermal load is
one of the main factors making the thermal following strategy less than
ideal.